Fore Street - Eastern Promenade Sewer Separation Project

PROJECT UPDATE:
This project has been advertised for bidding.  Bids for this project are due on Thursday, May 20th at 3:00pm.  If the construction contract is awarded it is anticipated that this project will commence around July 5th, 2021.   

Unitil Natural Gas has been onsite since mid April relocating their gas main in preparation of the City's project.  

This project has received funding approval as part of the Water Resources Capital Improvement Plan (CIP).  A target date of April 1, 2021 has been established to advertise the project for bidding.  If the project is successfully bid and awarded to the low bid contractor then it's anticipated the project will start around June 1, 2021.   


Fore St SD 2021-02-24 Facts Sheet
Fore Street 2020-01-21 Neighborhood Meeting Map
Project Name: Fore Street- Eastern Promenade Sewer Separation Project

Design Engineer: Woodard and Curran 

Owner: City of Portland Public Works Department

Contractor: TBD through the bidding process

Schedule: TBD

City Project Manager Contact Information:  
Justin Pellerin, P.E.  DPW Water Resources Project Engineer 